Project Milestones

There are many crucial steps that need to be taken before a highway can be built. From traffic surveys and environmental reports to engaging stakeholders and appointing contractors and consultants. Here are the milestones in the SUKE project.

17 March 2017

Launching of #contactlahkami

24 February 2017

Ground Breaking Ceremony for Balai Penghulu 1 at Ampang Jaya

25 August 2015

Pre Qualification and Tender Exercise

SUKE received the approval to acquire land for the purpose of constructing the highway under the Section 8, Land Acquisition Act 1960.
01 November 2013

2014: Public Opinion Survey and Soil Investigation Works

Soil Investigation Works were carried out from November 2013 to April 2014. A Public Opinion Survey (POS) was also done along affected areas from 14 February […]
25 September 2013

September 2013: CA Signing

The Concession Agreement was signed on 25 September 2013 between PROLINTAS and the government under the build-operate-transfer concept. The agreement includes the conditions that the company […]
01 April 2011

April 2011 – September 2013: Preliminary Design & Negotiation, and Approvals

SUKE received the Approval in Principle from UKAS for the construction of the Sungai Besi – Ulu Kelang Elevated Expressway on 1 April 2011. The team […]